Turnaround Cost Overrun Statistics: Where the "80% Fail" Number Came From

By MaintWiz Product Team · Published · 12 min read

Share
Shutdown Maintenance12 min read

Key takeaways

  • The "80% of turnarounds fail" figure has no traceable study, sample or definition, so cite it only as unverified.
  • AP-Networks reports that over two-thirds of turnarounds exceed planned cost and schedule by 10 percent or trip after startup.
  • The same database puts scope growth after freeze at 19 percent on average and 7 percent for top-quartile performers.
  • Your own last three turnarounds give a better budget basis than any industry figure.

Do 80% of turnarounds go over budget?

The turnaround cost overrun statistics behind "80% fail" do not trace to a study. We found no sample, no method and no definition of "fail". The best-sourced figure is different: AP-Networks reports that more than two-thirds of turnarounds exceed planned cost and schedule by 10 percent or have a trip after startup. Treat 80% as unverified.

This page lists each figure with its named source, says what it measures, and shows how a planner can build the same measures from plant history. Every statistic below names its source in the text. Figures we could not trace are marked unverified. Sources were read on 17 November 2026.

Where did the "80% of turnarounds fail" number come from?

It circulates in vendor blogs, conference decks and training slides, usually with the source removed. Where a source is given, it is T.A. Cook (a maintenance consultancy, acquired by Accenture in November 2021), sometimes together with Solomon Associates, dated 2019 (attributions reported by Reliable Media, ReliaMag). The claim comes in several forms:

  • 80 percent run more than 10 percent over budget.
  • 82 percent miss performance expectations.
  • About 50 percent are delayed.

Reliable Media (ReliaMag, "Turnaround Cost Overrun Statistics: Tracing the 80% Claim") followed the citations and reports that it could not locate the original study, a sample size or a methodology in any open source. We reached the same result. That does not prove the figure is wrong. It means nobody can check it, and a number nobody can check should not carry a budget decision.

Why the number still sounds right

Turnarounds are large, scope is uncertain and estimates are made early. Overruns are common, as the sourced data below shows. A figure that sounds plausible spreads without a source. Plausible is not the same as measured.

Which turnaround cost overrun statistics have a named source?

Two bodies of work are traceable, and they are different studies. Both come from AP-Networks (Asset Performance Networks), a turnaround benchmarking consultancy. The whitepaper centers on refining; its database also covers upstream, gas processing, chemicals and power generation. Gordon Lawrence's 2012 articles are a separate analysis of estimating accuracy.

AP-Networks whitepaper: scope and outcomes

FigureWhat it measuresNamed sourceRead this way
More than two-thirdsExceed planned cost and schedule by 10 percent, or have a trip after startupHansen and Schroeder, AP-Networks whitepaper "Benchmarking and Optimizing Maintenance Work Scope for Turnarounds"A composite of cost, schedule and trips. Not a pure cost-overrun rate.
40 percentCost overrun or schedule delay of more than 30 percentHansen and Schroeder, same whitepaperCost or schedule, either one.
19 percent vs 7 percentScope growth from scope freeze to execution, industry average vs top quartileHansen and Schroeder, same whitepaper, AP-Networks Turnaround Database of over 1,350 observationsScope, not cost. The strongest lever in the data.

Lawrence articles: estimate accuracy and work categories

FigureWhat it measuresNamed sourceRead this way
About 16 percentAverage cost overrun against the estimate (the OGJ article's word); range minus 27 to plus 43 percentGordon Lawrence, AP-Networks, Oil & Gas Journal, 2 April 2012Cost only. 2012 data.
83 percent intended plus or minus 10 percentSurvey answers: control budget meant as a plus or minus 10 percent estimateLawrence, PTQ, January 2012; survey at TINC Europe, Amsterdam, March 2011. The same article analyzes a sample of 93 recent turnaroundsIntent versus result: budgets behaved wider than intended.
Forgotten, emerging and discovery workThree categories of work added to a turnaround scopeLawrence, Oil & Gas Journal, 2 April 2012Definitions, not rates. Used in the tagging table below.

The whitepaper is undated in the file we read. The Lawrence articles are from 2012, so treat their numbers as a long-standing pattern, not a current rate.

What the figures do not tell you

None of them is a "failure rate". The two-thirds figure mixes three events. The 16 percent average hides a wide spread. No source we found breaks the figures out for mining, pharma or discrete plants. If your plant is outside process industries, the direction transfers, the numbers may not.

Why do turnarounds overrun?

The AP-Networks whitepaper names poor scope control as the first cause: significant work is added after the budget is set. Lawrence's articles add estimating practice. The definitions below let a planner tag growth in their own data.

TermMeaning (Lawrence, OGJ 2012)How to spot it in your records
Forgotten workKnown work left out of the basis of estimateOn the plant's job list or backlog at freeze, missing from the estimate
Emerging workWork from failures or leaks after scope freeze but before shutdownWork order raised between freeze date and shutdown start
Discovery workWork found only when equipment is opened in the shutdownWork order raised during execution, with an inspection finding as origin
AllowanceA cost you can tie to a specific line item in the estimateThe line item in the estimate, with the quantity or rate it assumed
ContingencyMoney that cannot be assigned to any specific line item; it covers costs running higher than estimated or unexpected activitiesThe reserve line in the budget, and how much of it was used

Lawrence (OGJ, 2 April 2012) writes that scope freeze typically occurs around 9 months before the shutdown. Anything added after that date is a change. Per Hansen and Schroeder, only top-quartile performers hold growth near 7 percent. If your scope-freeze date is not a hard gate, see freeze date and emergent work for how to set one.

When each kind of added work enters a turnaroundA timeline with scope freeze about nine months before shutdown. Forgotten work is known before the freeze, emerging work arises between freeze and shutdown, and discovery work is found during the shutdown. Scope freeze Shutdown typically about 9 months Forgotten work Known before the freeze, left out of the estimate Emerging work Failures or leaks after the freeze, before shutdown Discovery work Found only when the unit is opened in the shutdown
Figure 1. Forgotten work is a list failure before the freeze; emerging and discovery work arrive after it, which is why the change gate and the reserve matter (definitions: Lawrence, OGJ, 2 April 2012).

A change gate for work added after freeze

After the freeze, every added job answers four questions in order. You set the thresholds; the table shows who decides.

TestIf yesIf noWho decides
Is it needed for safety, a regulatory requirement, or a failure that would stop the unit before the next turnaround?Add itGo to the next testTurnaround manager with the inspection or safety lead
Can it wait for the next turnaround or an online window?Defer it and log it in the backlogGo to the next testPlanner
Does it sit on the critical path?State the added days and their cost of delay before approvalAbsorb it in the reserve if it fitsTurnaround manager
Is the added cost above the limit you set (hours or currency)?Escalate for approvalApprove and log the reasonSponsor, usually the plant manager

How much do turnaround budgets underestimate cost?

In the Lawrence analysis the average overrun against the estimate was about 16 percent, with individual turnarounds from 27 percent under to 43 percent over (Oil & Gas Journal, 2 April 2012). In the survey, 83 percent of respondents said their control budget was intended as a plus or minus 10 percent estimate. The other 17 percent said theirs included enough contingency to be a "not to exceed" number. None said plus or minus 30 percent.

Intended versus observed cost varianceA bar from minus 10 to plus 10 percent shows the intended accuracy; a much wider bar from minus 27 to plus 43 percent shows the observed range, with an average of plus 16 percent. Cost variance against the estimate Intended (83% of respondents): plus or minus 10% -10 to +10 Observed (OGJ, 2012): average +16%, range -27% to +43% avg +16 -27 +43 -30-20-100+10+20+30+40 Percent over (+) or under (-) the estimate
Figure 2. Budgets were meant to land within plus or minus 10 percent of the estimate; the observed range ran from minus 27 to plus 43 percent, with an average of plus 16 (Lawrence, OGJ, 2 April 2012; survey in PTQ, January 2012).

The gap between intent and result is the finding. Teams budgeted tight and delivered wide. The same OGJ analysis reports that teams included about 9 to 10 percent for allowances, while actual use was around 13 to 20 percent of the base cost, depending on the base used. Treat the allowance figures as directional: they come from a smaller subset whose size the article does not state. The direction is clear: the reserve was too small for the growth that arrived.

How can a planner use their own plant history instead?

Use your last three turnarounds. Industry averages describe other plants. Your records describe the way your plant scopes, estimates and discovers work. Five steps give you the same measures the benchmarks use.

  1. Export the job list as it stood on the scope-freeze date: jobs, planned hours, planned cost.
  2. Export the final list at close-out: jobs, actual hours, actual cost.
  3. Tag every added job as forgotten, emerging, discovery or owner-added scope, using the table above.
  4. Compute the measures in the next table.
  5. Repeat for the other two turnarounds and keep all three side by side.
MeasureFormulaCompares with
Scope growth(final planned hours of the scope list minus freeze hours) / freeze hoursAP-Networks: 19 percent average, 7 percent top quartile
Cost variance(actual cost minus estimate at scope freeze) / estimate at scope freezeLawrence: about 16 percent average
Emerging shareEmerging-work hours / freeze hoursYour own history only
Discovery shareDiscovery-work hours / freeze hoursYour own history only
Reserve usedHours or cost drawn from contingency / contingency includedYour own history only

Worked example (illustration)

All numbers here are an illustration, not data from any plant. At freeze: 52,000 planned hours and an estimate of 4,000,000. At close-out: 6,240 hours added, of which 2,600 emerging and 3,640 discovery, and actual cost 4,520,000.

  • Scope growth: 6,240 / 52,000 = 12 percent.
  • Cost variance: 520,000 / 4,000,000 = 13 percent.
  • Emerging share: 5 percent. Discovery share: 7 percent.

Cost of delay is the margin or output lost for each extra day the unit stays down. Direct overrun is not the full cost. Suppose the added hours sit on the critical path and a crew of 260 works 12 hours a day, which is 3,120 hours a day. The 6,240 added hours then push the finish out by 2 days (6,240 / 3,120). At a lost margin of 150,000 a day (illustration), the delay costs 300,000. Add the 520,000 direct overrun and the total is 820,000, or 20.5 percent of the estimate, not 13.

Suppose cost variance came out at 8 percent, 13 percent and 21 percent across three turnarounds (illustration). The median, 13 percent, is a starting reserve. The 21 percent is your stress case, and a reason to ask what drove it. Three data points are thin, and we say so. They are still your data, with your estimators, your equipment condition and your contract terms.

What a small sample can and cannot say

Three turnarounds will not give a statistical confidence range. They show whether your overruns cluster or swing. If they swing, the fix is process (a firm freeze, a change gate, a tagged emergent-work log), not a bigger number in the reserve line.

How does MaintWiz help with turnaround overrun tracking?

MaintWiz is an AI-powered CMMS built for Total Productive Maintenance. It does not replace your scheduling tool, and it does not replace SAP. It holds the records the baseline above is made from. Turnaround work is planned and run as work orders, with time logged on each work order, so the freeze-date and close-out lists you need for the calculation come from records you already keep.

Opening an asset shows its preventive maintenance, breakdown, spares and calibration history together, which is where discovery work leaves its trail: the finding on the last inspection, the failure before it. Your planner records why each added job was raised, and AI proposes while people approve. For the shutdown module, see shutdown management software for plants.

Customer success managers guide onboarding with Excel uploads of your asset and job history, and go-live takes 4 to 6 weeks. If you want to see a freeze list and a close-out list side by side on your own data, book a demo with the MaintWiz team.

What should a turnaround planner do about the other statistics in circulation?

Apply a short test to any figure before it goes into a deck or a business case.

QuestionPassFail
Is a named study or author given?Author, organization, title"Studies show", "industry data"
Is the sample stated?Number and type of eventsNo count
Is the measure defined?Cost, schedule or trip, with threshold"Fail", "miss expectations"
Does it match your industry and size?Same sector and complexityCapital projects used as turnarounds
Can you open the source?Public link or paperGated or missing

Capital-project statistics are a common source of drift: a figure measured on new-build projects gets quoted as if it described turnarounds. Check the population before you quote it.

FAQ

Is it true that 80% of turnarounds fail?

It is unverified. The figure is attributed to a 2019 T.A. Cook and Solomon Associates study, but no study, sample or definition has been found. The best-sourced figure is AP-Networks' finding that over two-thirds of turnarounds exceed planned cost and schedule by 10 percent or trip after startup.

What percentage of turnarounds exceed budget?

No source we could verify gives a clean over-budget rate. AP-Networks reports that 40 percent have a cost overrun or schedule delay above 30 percent. Lawrence reported an average cost overrun of about 16 percent against the estimate in AP-Networks data, with a range of minus 27 to plus 43 percent around it.

How much does turnaround scope grow after freeze?

AP-Networks reports an industry average of 19 percent growth from scope freeze to execution, against 7 percent for top-quartile performers, from a database of over 1,350 observations. The source is a consultancy whitepaper focused on refining, and the database also covers upstream, gas processing, chemicals and power.

How much contingency should a turnaround carry?

Start from your own history. Compute cost variance and emerging and discovery shares for your last three turnarounds, and set the reserve near the median with the highest case as a stress test. Lawrence (OGJ, 2012) found teams included about 9 to 10 percent while actual use ran 13 to 20 percent.

Why do turnaround budgets miss?

The named causes are scope added after freeze, work forgotten from the estimate, emerging and discovery work, and budgets treated as plus or minus 10 percent estimates when results behave wider. In the survey, 83 percent intended that accuracy.

Where can I find the original turnaround overrun data?

Read the AP-Networks whitepaper by Hansen and Schroeder, Gordon Lawrence's "Cost estimating for turnarounds" in PTQ (January 2012), and his analysis in Oil & Gas Journal (2 April 2012). Sources are listed below as plain text.

Sources

  • Shawn Hansen and Brett Schroeder, Asset Performance Networks (AP-Networks), "Benchmarking and Optimizing Maintenance Work Scope for Turnarounds", whitepaper, undated: https://www.ap-networks.com/wp-content/uploads/2021/11/WhitePaper-Benchmarking-and-Optimizing-Maintenance-Work-Scope-for-Turnarounds.pdf
  • Gordon Lawrence, AP-Networks, "Cost estimating for turnarounds", PTQ (Digital Refining), January 2012: https://www.digitalrefining.com/article/1000335/cost-estimating-for-turnarounds
  • Gordon Lawrence, AP-Networks, "Analysis yields turnaround benchmarks for allowance, contingency", Oil & Gas Journal, 2 April 2012: https://www.ogj.com/general-interest/article/17227163/analysis-yields-turnaround-benchmarks-for-allowance-contingency
  • Reliable Media, "Turnaround Cost Overrun Statistics: Tracing the 80% Claim", ReliaMag, undated: https://reliamag.com/guides/turnaround-cost-overrun-statistics/

Sources read 17 November 2026.

What to do first

  1. Remove "80% of turnarounds fail" from your slides, or label it unverified and attributed.
  2. Pull the freeze list and close-out list of your last three turnarounds.
  3. Tag every added job as forgotten, emerging, discovery or owner-added.
  4. Compute scope growth and cost variance, and compare them with 19 percent, 7 percent and about 16 percent, noting the sources.
  5. Set a hard freeze date and a change gate for the next event, using your own spread for the reserve. The shutdown execution page covers change control.