Shutdown KPIs: Formulas, Worked Examples and a Calculator

Short answer

Shutdown KPIs should cover cost and schedule with earned value measures (CV, CPI, SV, SPI, EAC), duration and scope growth against the baseline, and safety with both leading and lagging indicators. The formulas below come from the US GAO cost guide, BLS and NERC, with worked examples and a calculator.

How MaintWiz helps: You cannot improve what you measure after the shutdown ends. The MaintWiz shutdown module tracks earned value, cost and schedule indices and shows budget, actual and forecast cost in one view. See the module · Get the budget template

By · Published · Last reviewed

What MaintWiz adds:Earned value and cost indicesBudget, actual and forecast costCost by project and packageCumulative spend

The set

Which KPIs should a shutdown track?

A shutdown should track cost and schedule using earned value measures, duration and scope growth against the baseline, and safety using both leading and lagging indicators. The earned value formulas below are the standard definitions in the US Government Accountability Office cost guide. 1

MaintWiz: bubble chart of schedule index against cost index for each project
Schedule and cost index by project. A bubble chart titled Schedule and cost performance plots five running projects, P1 to P5, with schedule index across the bottom and cost index up the side. Bubble size is budget, ring colour is overall health and fill colour is the site: Refinery-A, Petrochem-B or Power-C.

Check which bubbles sit in the shaded corners. Top right is ahead and under budget; bottom left is behind and over budget. P1 sits furthest left on schedule index, so it is the first project to review. Use the position to decide where management attention goes in the progress meeting.

A KPI workbook that calculates these measures is in the shutdown planning templates. Earned value and index terms are defined in the shutdown turnaround glossary. Cost measures depend on a sound estimate: see how to estimate a shutdown budget.

BAC is the budget at completion, BCWS the planned value to date, BCWP the earned value and ACWP the actual cost. The cost and schedule numbers are the worked example from the budget guide: illustrative units on day 5 of a 10-day job.

Shutdown KPIs: formula, unit, worked example and basis
KPIFormulaWorked exampleBasis
Cost variance (CV)BCWP - ACWP392 - 441 = -49 (over budget)GAO cost guide
Cost performance index (CPI)BCWP / ACWP392 / 441 = 0.89GAO cost guide
Schedule variance (SV)BCWP - BCWS392 - 435 = -43 (behind plan)GAO cost guide
Schedule performance index (SPI)BCWP / BCWS392 / 435 = 0.90GAO cost guide
Estimate at completion (EAC)ACWP + (BAC - BCWP) / CPI441 + (870 - 392) / 0.89 = about 979GAO cost guide
Duration variance, %(actual days - planned days) / planned days x 100(11 - 10) / 10 = 10%Agreed definition
Scope growth, %(final work scope - frozen scope) / frozen scope x 100(940 - 870) / 870 = 8.0%Agreed definition
Recordable injury ratecases x 200,000 / hours worked7 x 200,000 / 400,000 = 3.5BLS incidence rate
Planned outage factor (power plants)planned outage hours / period hours x 100%480 / 8,760 = 5.5%NERC GADS Appendix F
Permits issued with hazards and controls adequately specified, %permits judged adequate / permits sampled x 10047 / 50 = 94%Indicator example in HSE HSG254

Agree the same terms with your team before you use the two definition rows. See the full worked example in shutdown budget planning.

Calculator

Can you check your own shutdown numbers?

Yes: enter your planned value, earned value, actual cost, durations, scope and injury data, and the calculator returns the eight KPIs defined in the table above.

The shutdown calculator tools page lists all the calculators with their inputs. To test a savings claim against your own baseline, see shutdown program ROI. The measures applied to an illustrative stop: shutdown case study planned vs actual. A free Excel file for this page: KPI workbook (.xlsx).

Try it: shutdown KPI calculator

Replace the starting numbers, which are the illustrative worked example, with your own. Nothing is sent or stored; the sums run in your browser.

Cost variance
Cost performance index
Schedule variance
Schedule performance index
Estimate at completion
Duration variance
Scope growth
Recordable injury rate

Software

Where should the KPI data come from?

KPI data should come from the same records that run the shutdown, so cost, progress and permits are measured once rather than re-typed into a report.

MaintWiz: close-out analytics on productivity, safety and comparison with earlier turnarounds
Close-out analytics. Three panels: Productivity by discipline, where above 1.0 is faster than planned; Safety, incidents by type with near miss at 3; and Against earlier turnarounds, comparing this project with the average of the four before it on duration, cost, scope growth and incidents.

Start with the comparison chart: it sets this project's duration, cost, scope growth and incidents beside the average of earlier turnarounds. Then use the discipline bars to see where productivity differed from plan. The result feeds the close-out review and the targets for the next turnaround.

Common questions about the module are answered in the shutdown module FAQ. See digital shutdown management for what to digitize first.

Also: product data sheet.

What the shutdown module covers

  • Shutdown calendar and critical-path scheduling, with work order sequencing and dependencies
  • Asset prioritization, so the most critical equipment is scoped first
  • Resource planning for people, spares, heavy equipment such as cranes, and outsourced vendors
  • Electronic permits to work, risk management and contingency plans
  • Real-time progress monitoring: schedule adherence, cost variance, quality metrics and risk factors
  • Step-by-step checklists, pre-restart testing protocols and post-shutdown analysis

Reading them

How do you read the indexes and variances?

A CPI or SPI above 1.0 is favorable, below 1.0 is unfavorable, and a negative variance means over budget or behind plan. Earned value is only as reliable as the progress data behind it: GAO warns that percent-complete estimates are subjective, especially for long activities. 2

MaintWiz: earned value chart with planned value, earned value, actual cost and forecast methods
Earned value: planned, earned and actual cost. A chart of planned value, earned value, actual cost and earned value forecast against a budget line of 1,415.6 M and a Today 8 Mar marker, with SV and CV labels, a Forecast final cost panel and an Earned value by discipline list.

Read the labels at the today line: SV is the schedule variance and CV the cost variance, so a negative SV with a positive CV means behind on schedule but not over on cost. The four forecast methods give different final costs; compare each with the budget line, then use the discipline list to find the lowest schedule index.

Float and critical path are worked by hand in critical path vs critical chain. For cost definitions, see planned vs unplanned shutdown cost. The schedule performance index is worked through in the shutdown S-curve and percent complete guide.

For example, GAO notes that 25 percent complete may be a viable estimate for a 4-day activity but is an ambiguous progress measure for a 50-day one. Break long jobs into short measurable steps. 2 GAO also cautions that earned value forecasts depend on reliable data and consistent baselines. 1

Index above 1.0

CPI or SPI > 1

The work cost less than planned (CPI) or progressed faster than planned (SPI).

Index below 1.0

CPI or SPI < 1

Over budget (CPI) or behind plan (SPI). At 0.89 CPI, each unit of earned value cost about 1.12 units.

Variance sign

negative = unfavorable

Cost and schedule variance are earned value minus actual or planned, so a negative number is bad news.

Benchmarks

Are there public benchmarks for shutdown KPIs?

On what is and is not public for refinery turnarounds, see T&I turnaround and inspection planning. For one published benchmark source, EIA, see nuclear refueling outage durations and for what is not public see shutdown program ROI. For the cost measures that drive overrun, see why shutdowns go over budget. Your own history is the benchmark: S/4HANA migration and maintenance history.

Comparing against peers needs matching definitions of what counts as scope, when the baseline was set and which hours are included, and published comparative data rarely says. The reliable comparison is your own previous shutdowns, measured the same way.

Safety

Why not rely on injury rate alone?

Injury rate counts harm that has already happened and says little about whether process safety controls are working. The CSB found that reliance on BP Texas City's low personal injury rate gave a misleading picture of process safety. 6

For T&I examples see T&I turnaround and inspection planning.

HSE's process safety indicator guide pairs a leading indicator with a lagging indicator for each critical control, so the first shows gaps found in routine checks and the second shows failures that have occurred. 5 See shutdown safety plan for example indicators.

Cadence

How often should shutdown KPIs be reported?

Report a few operating measures every shift, the earned value indexes daily, cost forecasts weekly on long events, and the full set at close-out.

Who reviews the KPIs is set out in shutdown team roles and RACI.

When to report which KPI
WhenKPIsPurpose
Every shiftPermits live and adequately specified; planned vs actual progress on critical-path jobsSteer the day
DailySPI, CPI, forecast duration, scope changes approvedDecide at the daily meeting
Weekly (multi-week events)EAC against budget plus contingency, scope growth, recordable casesReport to management
At close-outFinal duration variance, scope growth, cost variance, injury rate, lessonsFeed the next shutdown

Daily mechanics are in shutdown progress tracking; the close-out review is in shutdown lessons learned.

Visuals

Save the KPI cards

Two cards to pin up in the shutdown office. Click either for the full-size version.

FAQ

Frequently asked questions

What KPIs should I use to measure a shutdown?

Cost variance and cost performance index, schedule variance and schedule performance index, estimate at completion, duration variance against the baseline, scope growth, recordable injury rate and leading safety indicators. The earned value formulas are defined in the GAO cost guide. 1

How do you calculate cost performance index?

CPI = earned value divided by actual cost (BCWP / ACWP). With 392 earned and 441 spent, CPI is 0.89. 1

How do you calculate schedule performance index?

SPI = earned value divided by planned value (BCWP / BCWS). With 392 earned and 435 planned, SPI is 0.90. 1

What is estimate at completion?

A forecast of final cost: actual cost to date plus the remaining budget divided by an efficiency index such as CPI. In the example, 441 + (870 - 392) / 0.89 is about 979. 1

How do you calculate the injury rate?

Recordable cases multiplied by 200,000 and divided by hours worked by all employees. Seven cases over 400,000 hours is 3.5. 3

What is planned outage factor?

In NERC GADS reporting for generating units, planned outage hours divided by period hours, times 100%. 480 planned outage hours in an 8,760-hour year is 5.5%. 4

Are there industry benchmarks for shutdown performance?

Compare your own shutdowns, measured with the same definitions.

Why is injury rate not enough on its own?

Because it counts harm after the fact. The CSB found BP's low injury rate gave a misleading picture of process safety at Texas City, and HSE recommends pairing leading and lagging indicators. 6,5