Turnaround Progress Report: The One-Page Daily Layout and How to Read the S-Curve

By MaintWiz Product Team · Published · 13 min read

Share
Shutdown Maintenance13 min read

Key takeaways

  • A turnaround progress report is one page: status line, S-curve, critical path float, scope added, safety and decisions needed.
  • Weight percent complete by planned hours, or a small job counts as much as a major overhaul.
  • A gap on the S-curve shows lost time; critical path float shows whether the end date is actually at risk.
  • Leaders read the status line and the decisions block first, so write those last and keep them short.

What goes in a turnaround progress report?

A turnaround progress report is a one-page daily summary that tells leaders whether the shutdown will finish on time and what they must decide today. It holds six blocks: a status line, an S-curve of planned against actual progress, critical path float, scope added since the freeze, safety, and decisions needed. Everything else stays with the planner.

A common failure is the opposite: the report keeps growing, lists every activity, and buries the one number that matters. A leader who has to hunt for it stops looking. The fix is not a better chart. It is a fixed layout, a fixed time of issue, and the discipline to cut.

What belongs on the one page?

Put the answer first and the evidence under it. Each block exists to answer one question, and each draws on a record someone already keeps. If a block has no question behind it, drop it.

BlockQuestion it answersWhat goes in itWhere the data comes from
1. Status lineAre we on time?One sentence: on plan, at risk or late, with the forecast finish date and the reasonPlanner's judgment, written last
2. S-curveHow far behind or ahead are we?Planned and actual cumulative percent complete by day, gap in percentage pointsBaseline schedule and shift progress updates
3. Critical pathIs the end date threatened?Total float left on the longest chain and the next two near-critical chains; the three activities driving itScheduling tool
4. ScopeIs the work growing?Hours added since scope freeze, split into emergent and discovery work, and the hours approved versus waitingChange log tied to work orders
5. Safety and permitsIs anyone at risk?Incidents and near misses in the last 24 hours, open permits, any stop-work callsSafety log and permit register
6. Decisions neededWhat must a leader decide today?Each decision with owner, deadline and the cost of waitingDaily meeting notes

Two blocks do most of the work, the S-curve and the critical path. They answer different questions, and mixing them up is a common reading mistake.

How do you read a turnaround S-curve?

An S-curve plots cumulative planned progress against cumulative actual progress over the days of the shutdown. It is S-shaped because progress is slow at mobilization, fast in the middle when every crew is working, and slow again at close-out and commissioning. The gap between the two lines is the schedule gap in percentage points.

How is percent complete calculated?

Weight it by hours. The Interplan Systems turnaround planning primer describes the approach: each activity's percent complete is weighted by its manhour estimate against the total manhours for its work order. Weighting each work order by its share of total hours follows the same logic. A two-hour lubrication job then counts for little, and a boiler tube replacement counts for a lot. A simple count of finished jobs does the opposite, and flatters you early because small jobs finish first.

The earned figure on any day is the planned hours of work actually completed, plus the planned hours multiplied by percent complete for work in progress. Divide by total planned hours and you have the actual curve. Hold the planned curve fixed from the baseline. If you re-draw it each day, the gap vanishes and so does the warning.

What does each curve shape mean?

What you seeLikely causeWhat to check
Actual flat at the start, then catches upLate mobilization, permits or isolations not ready, materials not at sitePermit and isolation readiness at start; lay-down area and spares
Actual parallel to plan, below itA steady productivity shortfall, or an optimistic estimateCrew size against plan; hours per job against estimate
Actual falling further behind each dayGrowing scope, rework, or a resource bottleneckScope log; trades or equipment shared between jobs
Actual on plan, then flattens near the endLong tail of punch list, testing and commissioningOpen punch items; hold points waiting on inspection
Actual above planAhead, or progress claimed too earlySpot-check that finished work is signed off

The Interplan primer treats actual progress within 2 percent of plan as on schedule. That is one consultancy's rule, not a standard. Use it as a starting point and set your own band after your next turnaround.

Worked example (illustration)

All numbers below are an illustration. A ten-day turnaround has 40,000 planned hours. At the end of day 3 the plan says 18 percent should be done, and 12 percent is.

  • Gap: 12 minus 18 = 6 points behind.
  • Schedule performance index to date: 12 / 18 = 0.67. Earned value over planned value, the definition in the NASA PP&C glossary.
  • Planned rate for the remaining seven days, averaged: 82 / 7 = about 11.7 points a day (the real plan is S-shaped, so your daily figures will differ).
  • Rate now needed: 88 / 7 = about 12.6 points a day.

The index of 0.67 looks alarming. The forward rate needed is only about 8 percent above plan. That is the reading a leader needs: a slow start, recoverable if crews can lift output a little, and not a crisis by itself. Whether it is a crisis depends on the critical path, which the S-curve cannot show.

Turnaround S-curve at day 3: plan, actual and recovery rateCumulative percent complete over ten days. The plan reaches 18 percent on day 3 and the actual line 12 percent. A dashed line shows the average 12.6 points a day needed to finish on day 10. Cumulative percent complete 0% 50% 100% 0 1 2 3 4 5 6 7 8 9 10 Day of the turnaround (ILLUSTRATION) Plan (baseline, frozen) Actual Needed to recover Day 3: 12 vs 18, gap 6 points Needed to finish on day 10: about 12.6 points a day
Figure 1. The S-curve shows the gap, and the dashed line shows what closing it costs: 12 percent done against 18 planned on day 3 means about 12.6 points a day for seven days, against a planned peak of 14 (ILLUSTRATION, 40,000-hour plan).

In this illustration the busiest planned days add 14 points, so 12.6 is within reach if crews reach full strength early. If it needed more than the plan's own peak, the honest status line would say the date is at risk.

Why does critical path float matter more than the gap?

Because the end date follows the longest chain of dependent work, not the average. Total float is how many hours or days an activity can slip before it moves the finish. Per the NASA PP&C glossary, zero float means a delay to that activity delays the project by the same amount, and the critical path is the longest chain, with the least float. An S-curve can show you six points behind while the critical path is untouched, or show you on plan while the critical chain has already lost a day.

Report float for the critical chain and the next two near-critical chains, because a chain with a little float becomes critical after one small delay. Name the three activities driving each chain and who owns them. Keep the scheduling logic in your scheduling tool, such as Primavera P6 or Microsoft Project, and bring only the result onto the page.

Float on three chains and the effect of a slipThree chains of work against an eleven-day axis with planned finish on day 10. The reactor vessel chain has zero float, the exchanger bundle chain has 1 day, and piping tie-ins have 4 days. A 2-day slip on the exchanger chain moves the finish one day late. Planned finish Reactor vessel Float: 0 days Exchanger Float: 1 day Piping tie-ins Float: 4 days Critical chain: no spare time slip 2-day slip: finish 1 day late 4 days of float 0 1 2 3 4 5 6 7 8 9 10 11 Days from start (ILLUSTRATION)
Figure 2. Float is spare time, and a slip spends it before it moves the finish: the exchanger chain has 1 day, so a 2-day slip costs 1 day, while the same slip on piping tie-ins (4 days) costs nothing (ILLUSTRATION).

The S-curve is a lagging indicator: it reports work already done or missed. Float and scope added are leading indicators, because they warn before the finish date moves. Read the two together:

S-curve gapCritical floatWhat it meansStatus line
SmallHealthyOn trackOn plan
LargeHealthyBehind on work that is not driving the finish; watch itAt risk, recoverable
SmallShrinkingThe chain that counts is slipping while the average hides itAt risk; act on the chain
LargeGoneThe end date is movingLate; forecast a new date

What do leaders actually read?

The status line first, the decisions block second, and then the S-curve only if the status line worries them. Plant managers and operations directors are usually not auditing the schedule. They want to know what to say upward and what to approve today. A report that makes them hunt for either fails.

  • Write the status line last. One sentence with the forecast finish date and the reason. Example wording (illustration): "At risk: forecast finish 14 hours late, driven by late opening of the reactor vessel."
  • Make every decision a request. Owner, deadline, and the cost of waiting. Example wording (illustration): "Approve 12 extra riggers by 18:00 or the vessel inspection slips a shift."
  • Use the same layout every day. Leaders learn where to look. A moving layout costs them minutes every morning.
  • Show change, not totals. Yesterday's gap beside today's tells them if things are getting better.

What does waiting cost?

Cost of delay is the margin lost for each day the unit stays down beyond plan, plus standing costs such as contractor standby. It applies only to work on the critical chain, because a delay with float left moves nothing. Put it beside every decision so the leader compares two numbers.

ILLUSTRATION The vessel inspection is on the critical chain. Twelve extra riggers for one 10-hour shift at $70 an hour cost 12 x 10 x 70 = $8,400. If the inspection slips half a day (one 12-hour shift) and the unit earns $150,000 a day in margin, waiting costs 0.5 x $150,000 = $75,000. Waiting costs about nine times as much as acting ($75,000 / $8,400 = 8.9). The same riggers on a chain with 4 days of float would buy nothing.

On page one
  • Status line
  • S-curve gap in points
  • Critical path float
  • Scope added
  • Decisions needed
Stays with the planner
  • Every activity's percent
  • Hours by trade
  • Full activity log
  • Per-area charts
  • Contractor timesheets

What should you leave out?

Anything that does not answer one of the six questions. The planner needs the detail to run the event. The leader does not need it to decide. Keep it one click away, not on the page.

Leave outWhyDo this instead
Counts of activities finishedSmall jobs finish first and flatter the pictureHours-weighted percent complete
Percent complete for every areaTwelve charts hide the two that matterName only areas on or near the critical path
Lists of finished workGood news that changes no decisionMilestones reached, in one line
Cost to date without scope contextSpend follows progress; it says nothing aloneHours added since freeze, with approval status
Long narrativesA long narrative hides the answerThe status line plus the reason
A forecast with no reasonLeaders cannot challenge or act on itForecast date and the one driver

For the cost side of the same event, see the sourced figures in turnaround cost overrun statistics, and the formulas for the individual measures on the shutdown KPIs page.

What reporting rhythm works each day?

Four steps, repeated every shift or at least every day. The order matters: the update comes from the people doing the work, and the report is written only after the numbers are in.

  1. Update. Supervisors log finished work and an honest percent complete and remaining effort for work in progress, at a fixed cut-off time. Late updates get left out and flagged, not guessed.
  2. Calculate. Weighted percent complete, gap, forward rate needed and float.
  3. Write. One page. Status line last.
  4. Decide. The daily meeting opens on exceptions and decisions, not on a read-through.

Set the cut-off and the issue time once, before the shutdown, and keep them. An S-curve is only honest if the actual line is measured at the same moment each day, and the progress claimed is checked by someone who has seen the work.

How does MaintWiz help with turnaround progress reporting?

MaintWiz is an AI-powered CMMS built for Total Productive Maintenance. It does not replace your scheduling tool, which keeps the critical path logic, and it does not replace SAP. It holds the records the daily report is made from. Shutdown work is run as work orders, the entire work order lifecycle can be done in MaintWiz, and time is logged on each work order, so actual hours by job are there when the planner builds the actual curve.

Task progress shows as it happens, so work not yet done is visible. Reports and KPIs are configurable, and AI proposes while people approve. The shutdown management software page shows how turnaround work is organized, and maintenance project management covers planning and resources. Customer success managers guide onboarding with Excel uploads, and go-live takes 4 to 6 weeks.

If you want to see your last turnaround's work orders laid against a progress report, book a demo with the MaintWiz team.

FAQ

What is a turnaround progress report?

It is a short daily summary of how a turnaround stands against its baseline. It gives the status, planned against actual progress, critical path float, scope added, safety and the decisions leaders need to make. Keep it to one page and write it after the day's progress is in.

What is an S-curve in a turnaround?

It is a chart of cumulative planned and actual progress by day, shaped like an S because work starts slowly, peaks mid-event and tails off at close-out. The gap between the lines is the schedule gap. It shows progress in hours-weighted percent, not the critical path.

How is percent complete calculated in a turnaround?

Weight each activity by its planned hours, and each work order by its share of total hours, then add progress on work in progress. Counting finished jobs misleads because small jobs finish first. Measure at the same time every day, and check claims against signed-off work.

How often should a turnaround be reported?

At least daily, and after each shift on long or high-risk events. Fix the update cut-off and the issue time before the event starts. Leaders then know when to expect the page, and the actual line is always measured at the same moment.

What should leaders look at in a turnaround status report?

The status line, then decisions needed, then critical path float. The S-curve matters only when the status line signals risk. Float tells them if the end date is threatened, and the decisions block tells them what to approve before the day ends.

Is a 2 percent gap on the S-curve acceptable?

The Interplan Systems primer treats actual progress within 2 percent of plan as on schedule. That is a rule of thumb from one source, not a standard. Set your own band from past turnarounds, and always read the gap with critical path float.

Sources

The six-block layout, the worked example, the curve-shape table and the reading rules are our own method. The outside sources are below.

InterPlan Systems, "Turnaround Project Planning Primer: Reporting Progress", InterPlan Systems (copyright 2002-2013, no publication date shown); https://interplansystems.com/turnaround-project-planning-primer/reporting-progress.html

National Aeronautics and Space Administration, "PP&C Glossary" (entries: Schedule Performance Index, Total Float, Critical Path), NASA Office of the Chief Financial Officer, no date shown; https://www.nasa.gov/ocfo/ppc-corner/ppc-glossary/

Sources read 17 November 2026.

What to do first

  1. Draw the six-block page once, and agree the layout with the plant manager before the shutdown starts.
  2. Fix the update cut-off, the issue time and who checks claimed progress.
  3. Freeze the planned curve from the baseline, weighted by hours, and do not redraw it.
  4. Add critical path float for the main chain and two near-critical chains to every day's report.
  5. After the event, record your actual gap and float at each day and use it to set your own tolerance for next time.