Key takeaways
- A turnaround progress report is one page: status line, S-curve, critical path float, scope added, safety and decisions needed.
- Weight percent complete by planned hours, or a small job counts as much as a major overhaul.
- A gap on the S-curve shows lost time; critical path float shows whether the end date is actually at risk.
- Leaders read the status line and the decisions block first, so write those last and keep them short.
What goes in a turnaround progress report?
A turnaround progress report is a one-page daily summary that tells leaders whether the shutdown will finish on time and what they must decide today. It holds six blocks: a status line, an S-curve of planned against actual progress, critical path float, scope added since the freeze, safety, and decisions needed. Everything else stays with the planner.
A common failure is the opposite: the report keeps growing, lists every activity, and buries the one number that matters. A leader who has to hunt for it stops looking. The fix is not a better chart. It is a fixed layout, a fixed time of issue, and the discipline to cut.
What belongs on the one page?
Put the answer first and the evidence under it. Each block exists to answer one question, and each draws on a record someone already keeps. If a block has no question behind it, drop it.
| Block | Question it answers | What goes in it | Where the data comes from |
|---|---|---|---|
| 1. Status line | Are we on time? | One sentence: on plan, at risk or late, with the forecast finish date and the reason | Planner's judgment, written last |
| 2. S-curve | How far behind or ahead are we? | Planned and actual cumulative percent complete by day, gap in percentage points | Baseline schedule and shift progress updates |
| 3. Critical path | Is the end date threatened? | Total float left on the longest chain and the next two near-critical chains; the three activities driving it | Scheduling tool |
| 4. Scope | Is the work growing? | Hours added since scope freeze, split into emergent and discovery work, and the hours approved versus waiting | Change log tied to work orders |
| 5. Safety and permits | Is anyone at risk? | Incidents and near misses in the last 24 hours, open permits, any stop-work calls | Safety log and permit register |
| 6. Decisions needed | What must a leader decide today? | Each decision with owner, deadline and the cost of waiting | Daily meeting notes |
Two blocks do most of the work, the S-curve and the critical path. They answer different questions, and mixing them up is a common reading mistake.
How do you read a turnaround S-curve?
An S-curve plots cumulative planned progress against cumulative actual progress over the days of the shutdown. It is S-shaped because progress is slow at mobilization, fast in the middle when every crew is working, and slow again at close-out and commissioning. The gap between the two lines is the schedule gap in percentage points.
How is percent complete calculated?
Weight it by hours. The Interplan Systems turnaround planning primer describes the approach: each activity's percent complete is weighted by its manhour estimate against the total manhours for its work order. Weighting each work order by its share of total hours follows the same logic. A two-hour lubrication job then counts for little, and a boiler tube replacement counts for a lot. A simple count of finished jobs does the opposite, and flatters you early because small jobs finish first.
The earned figure on any day is the planned hours of work actually completed, plus the planned hours multiplied by percent complete for work in progress. Divide by total planned hours and you have the actual curve. Hold the planned curve fixed from the baseline. If you re-draw it each day, the gap vanishes and so does the warning.
What does each curve shape mean?
| What you see | Likely cause | What to check |
|---|---|---|
| Actual flat at the start, then catches up | Late mobilization, permits or isolations not ready, materials not at site | Permit and isolation readiness at start; lay-down area and spares |
| Actual parallel to plan, below it | A steady productivity shortfall, or an optimistic estimate | Crew size against plan; hours per job against estimate |
| Actual falling further behind each day | Growing scope, rework, or a resource bottleneck | Scope log; trades or equipment shared between jobs |
| Actual on plan, then flattens near the end | Long tail of punch list, testing and commissioning | Open punch items; hold points waiting on inspection |
| Actual above plan | Ahead, or progress claimed too early | Spot-check that finished work is signed off |
The Interplan primer treats actual progress within 2 percent of plan as on schedule. That is one consultancy's rule, not a standard. Use it as a starting point and set your own band after your next turnaround.
Worked example (illustration)
All numbers below are an illustration. A ten-day turnaround has 40,000 planned hours. At the end of day 3 the plan says 18 percent should be done, and 12 percent is.
- Gap: 12 minus 18 = 6 points behind.
- Schedule performance index to date: 12 / 18 = 0.67. Earned value over planned value, the definition in the NASA PP&C glossary.
- Planned rate for the remaining seven days, averaged: 82 / 7 = about 11.7 points a day (the real plan is S-shaped, so your daily figures will differ).
- Rate now needed: 88 / 7 = about 12.6 points a day.
The index of 0.67 looks alarming. The forward rate needed is only about 8 percent above plan. That is the reading a leader needs: a slow start, recoverable if crews can lift output a little, and not a crisis by itself. Whether it is a crisis depends on the critical path, which the S-curve cannot show.
In this illustration the busiest planned days add 14 points, so 12.6 is within reach if crews reach full strength early. If it needed more than the plan's own peak, the honest status line would say the date is at risk.
Why does critical path float matter more than the gap?
Because the end date follows the longest chain of dependent work, not the average. Total float is how many hours or days an activity can slip before it moves the finish. Per the NASA PP&C glossary, zero float means a delay to that activity delays the project by the same amount, and the critical path is the longest chain, with the least float. An S-curve can show you six points behind while the critical path is untouched, or show you on plan while the critical chain has already lost a day.
Report float for the critical chain and the next two near-critical chains, because a chain with a little float becomes critical after one small delay. Name the three activities driving each chain and who owns them. Keep the scheduling logic in your scheduling tool, such as Primavera P6 or Microsoft Project, and bring only the result onto the page.
The S-curve is a lagging indicator: it reports work already done or missed. Float and scope added are leading indicators, because they warn before the finish date moves. Read the two together:
| S-curve gap | Critical float | What it means | Status line |
|---|---|---|---|
| Small | Healthy | On track | On plan |
| Large | Healthy | Behind on work that is not driving the finish; watch it | At risk, recoverable |
| Small | Shrinking | The chain that counts is slipping while the average hides it | At risk; act on the chain |
| Large | Gone | The end date is moving | Late; forecast a new date |
What do leaders actually read?
The status line first, the decisions block second, and then the S-curve only if the status line worries them. Plant managers and operations directors are usually not auditing the schedule. They want to know what to say upward and what to approve today. A report that makes them hunt for either fails.
- Write the status line last. One sentence with the forecast finish date and the reason. Example wording (illustration): "At risk: forecast finish 14 hours late, driven by late opening of the reactor vessel."
- Make every decision a request. Owner, deadline, and the cost of waiting. Example wording (illustration): "Approve 12 extra riggers by 18:00 or the vessel inspection slips a shift."
- Use the same layout every day. Leaders learn where to look. A moving layout costs them minutes every morning.
- Show change, not totals. Yesterday's gap beside today's tells them if things are getting better.
What does waiting cost?
Cost of delay is the margin lost for each day the unit stays down beyond plan, plus standing costs such as contractor standby. It applies only to work on the critical chain, because a delay with float left moves nothing. Put it beside every decision so the leader compares two numbers.
ILLUSTRATION The vessel inspection is on the critical chain. Twelve extra riggers for one 10-hour shift at $70 an hour cost 12 x 10 x 70 = $8,400. If the inspection slips half a day (one 12-hour shift) and the unit earns $150,000 a day in margin, waiting costs 0.5 x $150,000 = $75,000. Waiting costs about nine times as much as acting ($75,000 / $8,400 = 8.9). The same riggers on a chain with 4 days of float would buy nothing.
- Status line
- S-curve gap in points
- Critical path float
- Scope added
- Decisions needed
- Every activity's percent
- Hours by trade
- Full activity log
- Per-area charts
- Contractor timesheets
What should you leave out?
Anything that does not answer one of the six questions. The planner needs the detail to run the event. The leader does not need it to decide. Keep it one click away, not on the page.
| Leave out | Why | Do this instead |
|---|---|---|
| Counts of activities finished | Small jobs finish first and flatter the picture | Hours-weighted percent complete |
| Percent complete for every area | Twelve charts hide the two that matter | Name only areas on or near the critical path |
| Lists of finished work | Good news that changes no decision | Milestones reached, in one line |
| Cost to date without scope context | Spend follows progress; it says nothing alone | Hours added since freeze, with approval status |
| Long narratives | A long narrative hides the answer | The status line plus the reason |
| A forecast with no reason | Leaders cannot challenge or act on it | Forecast date and the one driver |
For the cost side of the same event, see the sourced figures in turnaround cost overrun statistics, and the formulas for the individual measures on the shutdown KPIs page.
What reporting rhythm works each day?
Four steps, repeated every shift or at least every day. The order matters: the update comes from the people doing the work, and the report is written only after the numbers are in.
- Update. Supervisors log finished work and an honest percent complete and remaining effort for work in progress, at a fixed cut-off time. Late updates get left out and flagged, not guessed.
- Calculate. Weighted percent complete, gap, forward rate needed and float.
- Write. One page. Status line last.
- Decide. The daily meeting opens on exceptions and decisions, not on a read-through.
Set the cut-off and the issue time once, before the shutdown, and keep them. An S-curve is only honest if the actual line is measured at the same moment each day, and the progress claimed is checked by someone who has seen the work.
How does MaintWiz help with turnaround progress reporting?
MaintWiz is an AI-powered CMMS built for Total Productive Maintenance. It does not replace your scheduling tool, which keeps the critical path logic, and it does not replace SAP. It holds the records the daily report is made from. Shutdown work is run as work orders, the entire work order lifecycle can be done in MaintWiz, and time is logged on each work order, so actual hours by job are there when the planner builds the actual curve.
Task progress shows as it happens, so work not yet done is visible. Reports and KPIs are configurable, and AI proposes while people approve. The shutdown management software page shows how turnaround work is organized, and maintenance project management covers planning and resources. Customer success managers guide onboarding with Excel uploads, and go-live takes 4 to 6 weeks.
If you want to see your last turnaround's work orders laid against a progress report, book a demo with the MaintWiz team.
FAQ
What is a turnaround progress report?
It is a short daily summary of how a turnaround stands against its baseline. It gives the status, planned against actual progress, critical path float, scope added, safety and the decisions leaders need to make. Keep it to one page and write it after the day's progress is in.
What is an S-curve in a turnaround?
It is a chart of cumulative planned and actual progress by day, shaped like an S because work starts slowly, peaks mid-event and tails off at close-out. The gap between the lines is the schedule gap. It shows progress in hours-weighted percent, not the critical path.
How is percent complete calculated in a turnaround?
Weight each activity by its planned hours, and each work order by its share of total hours, then add progress on work in progress. Counting finished jobs misleads because small jobs finish first. Measure at the same time every day, and check claims against signed-off work.
How often should a turnaround be reported?
At least daily, and after each shift on long or high-risk events. Fix the update cut-off and the issue time before the event starts. Leaders then know when to expect the page, and the actual line is always measured at the same moment.
What should leaders look at in a turnaround status report?
The status line, then decisions needed, then critical path float. The S-curve matters only when the status line signals risk. Float tells them if the end date is threatened, and the decisions block tells them what to approve before the day ends.
Is a 2 percent gap on the S-curve acceptable?
The Interplan Systems primer treats actual progress within 2 percent of plan as on schedule. That is a rule of thumb from one source, not a standard. Set your own band from past turnarounds, and always read the gap with critical path float.
Sources
The six-block layout, the worked example, the curve-shape table and the reading rules are our own method. The outside sources are below.
InterPlan Systems, "Turnaround Project Planning Primer: Reporting Progress", InterPlan Systems (copyright 2002-2013, no publication date shown); https://interplansystems.com/turnaround-project-planning-primer/reporting-progress.html
National Aeronautics and Space Administration, "PP&C Glossary" (entries: Schedule Performance Index, Total Float, Critical Path), NASA Office of the Chief Financial Officer, no date shown; https://www.nasa.gov/ocfo/ppc-corner/ppc-glossary/
Sources read 17 November 2026.
What to do first
- Draw the six-block page once, and agree the layout with the plant manager before the shutdown starts.
- Fix the update cut-off, the issue time and who checks claimed progress.
- Freeze the planned curve from the baseline, weighted by hours, and do not redraw it.
- Add critical path float for the main chain and two near-critical chains to every day's report.
- After the event, record your actual gap and float at each day and use it to set your own tolerance for next time.