Failed Restart After a Shutdown: What Owners Should Do

Short answer

Under OSHA 29 CFR 1910.119(m), an incident that caused or could reasonably have caused a catastrophic release must be investigated, starting as promptly as possible and no later than 48 hours after it. A team including someone who knows the process writes a report with contributing factors and recommendations, resolves each finding, shares it with affected staff, and keeps it five years. Review changes through management of change and the pre-startup review before trying again.

How MaintWiz helps: The MaintWiz shutdown module carries this work as work packages with checklists, readings and photos, permits and readiness gates, so the result stays with the work order.

By · Technical review: Murali Nerur Pasupathy · Published · Last reviewed

What MaintWiz adds:Critical path and floatReadiness gatesPermits and isolationsChecklists with readings

OSHA duties

What does OSHA PSM require after a failed restart?

The 48 hours is the latest time to begin the investigation, not the time to finish the report.

OSHA PSM duties after a failed restart
DutyWhat it requires (paraphrased)TimingParagraph
Incident investigationInvestigate incidents that caused or could reasonably have caused a catastrophic releaseStart no later than 48 hours after the incident1910.119(m)(1)-(2)
Investigation teamAt least one person who knows the process, a contractor employee if relevant, others with expertiseWith the investigation1910.119(m)(3)
Report and follow-upRecord the dates, description, contributing factors and recommendations; resolve and document actions; review with affected staffResolve promptly; keep the report 5 years1910.119(m)(4)-(7)
Management of changeWritten MOC for changes other than replacement in kind; train affected people before restartBefore the change and before restart1910.119(l)
Pre-startup safety reviewConfirm equipment, procedures and training before hazardous chemicals are introduced after a significant modificationBefore chemicals are re-introduced1910.119(i)

Actions

What should the owner do in the first days?

Protect the evidence, start the investigation and do not restart on the same assumptions.

  • Make the unit safe and keep the evidence: logs, trends, procedures, permits and phone instructions.
  • Start the investigation within 48 hours with a team that includes someone who knows the process and, if contractors worked on it, a contractor employee.
  • Record the contributing factors, not only the immediate cause, and write the recommendations.
  • Treat repair changes as changes: run management of change and update procedures and training before restart.
  • Run the pre-startup review again where the repair is a significant modification.
  • Learn from public cases: after BP Texas City (2005), the US Chemical Safety Board found abnormal start-ups had not been investigated and a key instruction was given by phone and not logged.
  • UK HSE guidance notes that many hazards arise at start-up or shut-down and these phases need specific procedures kept current through controlled change.

FAQ

Frequently asked questions

Must an aborted start-up be investigated under OSHA PSM?

If it caused or could reasonably have caused a catastrophic release of a highly hazardous chemical, yes, and the investigation must start within 48 hours.

Does the 48 hours mean the report is due in 48 hours?

No. The 48 hours is the latest time to begin the investigation. The rule sets no deadline for finishing the report.

How long are investigation reports kept?

Five years under 1910.119(m).

When does a repair after a failed start-up need MOC and a pre-startup review?

MOC applies to changes other than replacement in kind; a pre-startup review applies to modifications significant enough to require updated process safety information. Both are completed before the process is restarted.