Skip to content
MaintWiz: Innovating Industrial AI

Equipment guide

Heat Exchanger Turnaround Planning: Bundle Pull Sequence and Job Card

Short answer

Heat exchanger turnaround planning sequences each exchanger through isolation, bundle pull, cleaning, inspection, repair or retubing, reassembly, pressure test and reinstatement on one job card. Plan the crane lift and the cleaning pit first, because they are shared by every exchanger. MaintWiz holds each exchanger as a work package with checklists and findings.

Plugging limits, test pressure and repair methods come from the engineer and the code.

How MaintWiz helps: Dozens of exchangers share one crane and one cleaning pit. The MaintWiz shutdown module gives plant teams one plan for scope, schedule, permits, spares and execution, from the first work package to close-out. See the module · Get the exchanger job card

By · Published · Last reviewed

What MaintWiz adds:Scope, schedule and permits in one planSpares status with SAPReadiness gatesFindings to the planner

Definition

What is heat exchanger turnaround planning?

Heat exchanger turnaround planning decides which exchangers to clean, inspect, repair, retube or replace in the stop, and sequences each one through isolation, bundle pull, cleaning, inspection, repair, reassembly, test and reinstatement with a job card, a lift plan and a cleaning pit.

Exchangers are repetitive work with shared constraints: one crane, one cleaning pit, one hydroblasting crew and one set of inspectors. A refinery or chemical turnaround can have dozens of them, so the sequence and the shared resources decide the finish date more than any single exchanger does.

Download the free heat exchanger job card sheet (Excel) for a twelve-step job card and an exchanger list that checks plugging against the engineer’s limit.

Sequence

What is the task sequence for a heat exchanger turnaround?

The task sequence for an exchanger is permit and isolation, open and pull the bundle, clean, inspect, repair or retube, reassemble with new gaskets, pressure test and reinstate, and each step has its own resource, so the job card follows the unit through all of them. 2,3

Shell-and-tube heat exchanger with the tube bundle pulled out and six numbered job steps marked
A heat exchanger bundle pull in six steps. A side view of a shell-and-tube exchanger with a crane lifting the tube bundle clear of the shell. Six numbered markers run from isolate and blind, through channel cover removal, extractor and crane set-up, the pull, the cleaning pit and hydroblasting.

Follow the markers in order when you build the task list for the exchanger. Isolation and blinding come before anything is opened, and the crane and extractor set-up fixes the lift window. The cleaning pit and hydroblast steps need their own booking, so schedule them as separate tasks, not as part of the pull.

A heat exchanger bundle pull in six steps: text version
MarkerWhat it marksNote
1Isolate and blindBoth nozzles
2Remove channel cover and bolting
3Set up bundle extractor and crane lift
4Pull the bundle
5Move bundle to cleaning pit
6Hydroblast tubes and shell

Illustration by MaintWiz with numbered markers.

Related: Hydrotest and leak test planning · Turnaround scaffolding planning

  1. 1

    Isolate and prepare

    Drain, purge, blind and test the atmosphere under a permit.

    Permit
  2. 2

    Open and pull the bundle

    Remove heads and bolting; plan the lift and the laydown.

    Lift
  3. 3

    Clean

    Hydroblast tubes and shell at a controlled cleaning pit.

    Pit
  4. 4

    Inspect

    Visual and tube testing; record findings by tube.

    Data
  5. 5

    Repair or retube

    Plug, retube or replace as the engineer decides.

    Decision
  6. 6

    Reassemble and test

    New gaskets, bolting to procedure, pressure test, reinstate.

    Close

Isolation, blinding and lockout follow your procedures and the guidance. See permit management and the HSE guidance on safe isolation. 2 Entering a channel or shell is a confined space entry where the rules apply. 4

MaintWiz

How does MaintWiz plan repetitive exchanger work?

MaintWiz holds each exchanger as a work package with checklists, readings, photos and findings that reach the planner, and shows shared resources such as cranes and crews against demand; AI agents support shutdown planning.

Bring your exchanger list to a demo and we will load the job cards. Tell us how you sequence the pit and the crane.

What the shutdown module covers

  • Work packages with steps, parts, labor and drawings
  • Permits and isolations shown on each work order
  • Checklists with readings and photos for technicians
  • Findings from technicians sent straight to the planner
  • Gantt chart with critical path, float and baselines
  • Trade and tool availability by week

Decide

Should you clean, repair, retube or replace a heat exchanger?

Decide from inspection data and the engineer’s limits: clean and return when tubes and shell are within limits, plug a few failed tubes while plugging stays under the limit, retube when many tubes are at end of life and the shell is sound, and replace when damage is beyond repair.

Clean, plug, retube or replace?
DecisionWhen it fitsPlanning impact
Clean and returnInspection shows tubes and shell within limitsShortest. Pit and crane time only
Plug tubesA few failed tubes and plugging stays within the engineer’s limitAdds inspection and plugging time
RetubeMany tubes at end of life and the shell is soundNeeds a tube specialist, material and test; order early
Replace the bundleDamage beyond repair, or a process changeLong lead item; fabricate ahead and fit the lift

Decide the likely outcome before the stop from the inspection history and order the tubes or the bundle if it is likely, because delivery is long and the stop is short.

Inspection

How are heat exchanger tubes inspected during a turnaround?

Tubes are cleaned first and then inspected visually and by tube testing such as eddy current or internal rotary inspection, chosen by the tube material, with the findings recorded by tube so the engineer can decide on plugging, retubing or replacement. 1

Tube inspection methods
MethodWhat it findsPlanning note
Visual of channel, tubesheet and bundleCorrosion, fouling, damaged gaskets, pittingDo it as soon as the bundle is out
Eddy current testingWall loss and cracks, mostly in non-ferromagnetic tubesNeeds clean tubes and a trained operator
Internal rotary inspection (IRIS)Wall thickness in many tube materialsNeeds clean and water-filled tubes
Hydrostatic leak testLeaking tubes and jointsSee hydrotest planning

Which method fits which tube material is an inspector’s decision. Book the inspector and the equipment with the cleaning plan so tubes are clean when the inspector is ready.

Cleaning pit

How do you plan an exchanger cleaning pit?

Plan the cleaning pit as a shared resource: size it for the number of bundles, site it near the lift path, contain and treat the wash water, set an exclusion zone around the water jetting, and schedule bundles through it in the order the exchangers are needed.

  • Place the pit near the crane path and the laydown
  • Contain wash water and plan its disposal
  • Set an exclusion zone and permit for water jetting
  • Queue bundles by priority and critical path
  • Provide lighting, drainage and welfare
  • Track bundles in and out on one board

Job card

What goes on a heat exchanger job card?

A heat exchanger job card lists the twelve steps from permit to reinstatement with the resource and the planned hours for each, the isolation points, the lift plan, the inspection results, the plugging count against the engineer’s limit and the test result.

Preview of the heat exchanger job card sheet: each step with its resource, planned hours, predecessor check and actual hours
The job card, step by step. The sheet heat-exchanger-turnaround-job-card-sheet.xlsx lists six steps, from permit, isolation, drain, purge and gas test to hydroblasting tubes and shell. Columns are Step, Description, Resource, Planned hours, Predecessors done? (Yes/No) and Actual hours; the last three are left empty for the planner.

Read the Resource column first to see which crew owns each step, from the permit issuer through fitters and riggers to the cleaning crew. The planner then fills in planned hours and confirms the predecessor is done before a step starts. Actual hours go in afterwards for comparison with the plan.

The job card, step by step: text version
Column shown
Step
Description
Resource
Planned hours
Predecessors done? (Yes/No)
Actual hours

Each step records a resource, planned hours, whether predecessors are done, and actual hours.

Related: Hydrotest and leak test planning · Turnaround scaffolding planning · Shutdown work packages

Job card sections
SectionContents
IdentityTag, service, drawings, bundle weight and type
IsolationPoints, blinds, permit number
Lift planCrane, extractor, laydown, route
Steps and hoursTwelve steps with resource and planned hours
InspectionFindings by tube, photographs
DecisionClean, plug, retube or replace, signed by the engineer
Test and reinstatementTest result, blinds removed, sign-off

Use the job card to feed the work package. See work package optimization.

Visuals

Save the exchanger planning visuals

Two visuals for the exchanger planner. Click either for the full-size image.

FAQ

Frequently asked questions

What is the task sequence for a heat exchanger turnaround?

Permit and isolation, open and pull the bundle, clean, inspect, repair or retube, reassemble with new gaskets, pressure test and reinstate.

How long does a heat exchanger turnaround job take?

It depends on size, access, cleaning and repair. Build the duration from the twelve job card steps and your own history.

When should you retube instead of replace a bundle?

When many tubes are at end of life and the shell and tubesheet are sound. The engineer decides from the inspection data.

How do you inspect heat exchanger tubes?

Clean first, then inspect visually and by tube testing such as eddy current or internal rotary inspection, chosen by tube material.

What is a tube plugging limit?

The share of plugged tubes the engineer allows before the exchanger must be retubed or replaced. It is set for each exchanger.

Why plan the cleaning pit?

It is a shared resource. Placement, wash water, the exclusion zone and the order of bundles decide how fast the exchangers move.

What goes on an exchanger job card?

Identity, isolation, lift plan, twelve steps with hours, inspection findings, the decision, the test and reinstatement.

Is there a free exchanger job card?

Yes. The heat exchanger job card sheet (Excel) has the twelve-step job card and an exchanger list that checks plugging against the limit.

Does MaintWiz plan exchanger work?

It holds each exchanger as a work package with checklists, findings and resource demand. AI agents are part of the module. See AI shutdown planning.

Plan your next shutdown in one system

Book a demo and tell us about your plant. We will show how the module handles your shutdown.

Book a demo