Safety KPIs

Shutdown Safety KPI Targets: TRIR, DART and Near Misses

Short answer

TRIR is recordable cases times 200,000 divided by hours worked, the 200,000 representing 100 full-time workers for a year. DART uses only cases with days away, restriction or transfer. Do not invent a benchmark: compare with the US Bureau of Labor Statistics 2024 rate for your industry (private industry 2.3 recordable and 1.4 DART per 100 workers), then set a target against your own history.

How MaintWiz helps: The MaintWiz shutdown module carries this work as work packages with checklists, readings and photos, permits and readiness gates, so the result stays with the work order.

By · Technical review: Murali Nerur Pasupathy · Published · Last reviewed

What MaintWiz adds:Critical path and floatReadiness gatesPermits and isolationsChecklists with readings

Formulas

How are TRIR and DART calculated?

Both use the same base of 200,000 hours, which equals 100 full-time workers over a year.

TRIR and DART formulas
MeasureFormulaWorked example (illustration)Basis
Total recordable incident rate (TRIR)Recordable cases x 200,000 / hours worked7 x 200,000 / 400,000 = 3.5BLS
DART rate(Days-away cases + restricted or transferred cases) x 200,000 / hours worked3 x 200,000 / 400,000 = 1.5 for three such casesBLS, OSHA

Only hours actually worked count; paid time not worked, such as holiday and sick leave, is excluded.

Industry rates

What are typical industry rates to compare with?

BLS 2024 rates per 100 full-time workers, released 22 January 2026; they are all-year, all-employer averages, not turnaround-specific.

BLS 2024 incidence rates per 100 full-time workers, private industry
Industry (NAICS)Total recordable casesDART (days away, restriction or transfer)
Private industry2.31.4
Manufacturing (31-33)2.71.7
Chemical manufacturing (325)1.61.0
Petroleum and coal products manufacturing (324)1.00.6
Support activities for mining (213)0.90.7
Utilities (22)1.91.2
Construction (23)2.21.3
Heavy and civil engineering construction (237)1.81.0
Specialty trade contractors (238)2.31.4
Primary metal manufacturing (331)3.32.0
Paper manufacturing (322)2.41.6

Oil and gas extraction (211) is not published for 2024. No public source gives a turnaround-specific benchmark.

Targets

How should you set the target for a shutdown?

Use your own history first, then the industry rate, then leading indicators.

  • Take the last shutdowns on the same site as the baseline, with the same counting rules and hours including contractors.
  • Compare with the BLS rate for your industry and set a target that improves on both your history and the industry rate.
  • Do not use a near-miss ratio as a target: Heinrich's 1:29:300 is questioned and Bird's studies gave other ratios. Set a minimum reporting expectation and track reports as a leading indicator.
  • Add process safety indicators: the US Chemical Safety Board found BP relied on injury statistics while process safety performance declined, and UK HSE publishes HSG254 on leading and lagging indicators.
  • Report permits issued with hazards and controls adequately specified as a leading indicator of permit quality.

FAQ

Frequently asked questions

How is TRIR calculated?

Recordable cases times 200,000 divided by hours worked. The 200,000 stands for 100 full-time workers for a year.

What does DART include?

Cases with days away from work, restricted work or job transfer, on the same 200,000 basis.

What is a good TRIR target for a shutdown?

No public source gives a universal target. Compare with the BLS rate for your industry, use your own recent shutdowns as the baseline and set a target that improves on both.

What should the near-miss ratio be?

There is no verified standard ratio. Track near-miss reports as a leading indicator of reporting culture and set a minimum reporting expectation instead of a ratio.

Are injury rates enough to judge shutdown safety?

No. The US Chemical Safety Board found that relying on injury statistics hid declining process safety at BP Texas City, so pair injury rates with process safety indicators.

Plan this work in the shutdown module

Book a demo and bring your next shutdown scope. We will show how the work, the permits and the results sit in one plan.