Mining Shutdown Software for Mill Relines and Plant Stops

Short answer

Mining shutdown software plans a processing plant stop around the mill reline. In MaintWiz the reline sets the critical path and other plant jobs fit in its float, readiness gates check liner kits, tools and permits before the window opens, heavy lifts and shared tools are scheduled by crew and day, and every shift hands over with a note and an as-left summary on the work order, so the next crew picks up an unfinished lift safely.

How MaintWiz helps: MaintWiz is a comprehensive shutdown solution for mines and concentrators. It has the reline kits, lifts and crews ready before the window opens and carries every job across the shift change.

  • Scope, plan, schedule, execution and close-out in one module
  • Critical-path Gantt with float and baselines
  • Seven readiness gates, signed off by name
  • Integrated ePTW: permits and LOTO isolations on every work order
  • Earned value: planned, earned and actual, with cost and schedule indices
  • Spares needed, in stock and short, with SAP status
  • Mobile work orders, offline on transaction screens
  • 15 AI agents propose each day; your people approve

By · Technical review: Murali Nerur Pasupathy · Published · Last reviewed

What MaintWiz adds:Reline on the critical pathLiner kit readinessShared lifts by crewHandover on every job

The reline

What makes a mill reline shutdown hard to hold to the hour?

A short window, repeated often, with one critical job and shared heavy lifts.

Liner and tool readiness

Liner kits, bolts and relining tools must be staged before the stop.

Heavy-lift clashes

The reline and other jobs need the same cranes and access.

Shift handovers

A lift left unfinished at shift change is the riskiest moment of the stop.

Early liner failure

An unplanned reline arrives before the plan is ready.

US surface-mine rules require repairs or maintenance to be done only after the power is off and the machinery is blocked against hazardous motion. 1 UK HSE notes that many accidents at shift handover involved planned maintenance work. 2

MaintWiz

How does MaintWiz run a mill reline shutdown?

The shutdown superintendent's problems, each with its screen.

Mill reline shutdown problems and the MaintWiz answer
Your problemWhat MaintWiz does
Heavy-lift clashesShared tool pools, availability by week and the look-ahead by crew
Shift handoverShift handover lists, and a handover note and as-left summary on every work order
Liner and tool readinessReadiness gates for materials, tools and permits, and kit readiness by package
Critical path and floatGantt, driving path and float flag, with the reline as the path
Inspections in the windowInspection packages planned with permits and gates
MaintWiz: kit readiness by work package
Kit readiness by package. Three panels: Spares position against stock, PO issued, PR raised and no request; Kit readiness by package, counting Planned 105, Picking 39, Staged 25 and Issued 151; and a list of kits to stage in the next 4 days with work package IDs.
MaintWiz: field board showing the shift by crew with one bar selected
The shift by crew (field board). A time chart of the 12-hour shift from 06:00 to 18:00 with task bars for each crew: In-house crews, Apex Mechanical, Sterling NDT, Voltaic Electrical and ThermoServe. Colours mark ready, in progress, complete and blocked; a red outline marks critical.
MaintWiz: float map by unit and discipline, coloured by least float, with today line and driving chain
Float map. Rows are units and disciplines, columns are days, and each cell's colour is the least float of the work running then: red critical, orange near-critical, blue shades for float to 10, 10 to 20 and over 20 days, green complete. A dashed line follows the driving chain.

Repeat relines

How does MaintWiz handle relines that come round every few months?

Each reline is a project in the same history, so the next one starts from the last.

Last reline on record

Duration, crew hours and lessons from the previous reline.

Against earlier ones

Compare this reline with the last on duration and incidents.

Early failure

Bring an unplanned reline forward from the last plan and re-check the gates.

Kits staged

Kit readiness by package shows what is still missing.

Measures

What should you measure in a reline?

A few measures tell you whether the reline went well; MaintWiz reads them from the same plan the field updates.

Reline hours against plan

Mill back on feed against the planned hour.

Mill availability after return

Running time in the weeks after the stop.

Liner life

Hours or tonnes achieved by the liner set.

Incidents

Lifting and isolation incidents and near misses.

Kits ready at the start

Liners, bolts and tools staged before the window opened.

Worked example

Worked example: an unfinished lift at shift change

ILLUSTRATION: an 18-day concentrator shutdown with the SAG mill reline as the critical path; flotation and thickener work fits in its float.

  1. 1Kits checkedLiners, bolts and tools pass the gates
  2. 2Reline startsCritical path; other jobs in float
  3. 3Shift ends mid-liftLift rigged, not landed
  4. 4Handover on the jobNote and as-left summary on the work order
  5. 5Next crewPicks up the lift with the facts in hand
ILLUSTRATION: the reline as critical path, and one lift carried safely across the shift change.
The handover note lives on the work order, so the incoming crew reads it where the work is.

One system

Why run the reline inside the CMMS?

The reline uses the same equipment, spares and permits as everyday maintenance; keeping them in one system removes the re-keying between tools.

Work orders and history

Every reline job is a work order on the same equipment record, so findings and repairs stay in the asset's history.

Spares and SAP

Needed, in stock and short come from the same stores data, with the SAP request or order behind each short part.

Permits and isolations

ePTW permits and isolations sit on each work order, and a package cannot close while one is open.

AI agents with an approver

AI agents review scope, estimates and the schedule and write daily summaries; each proposal has a named person who approves it.

Who uses it

Who uses MaintWiz in a reline?

Each role sees its own part of one plan, so nobody works from a copy.

Who uses MaintWiz in a reline
RoleWhat they seeWhat they decide or record
Site general managerRestart hour and costDecisions on extensions
Maintenance superintendentCritical path, lifts and readinessDaily priorities and crews
Shutdown plannerFloat, kits and the last relineSequence of other plant jobs
Reline contractorTheir jobs and the handover notesProgress and as-left state
OperationsIsolations and permitsRelease and restart

Getting started

How do you start from your last reline plan?

Start from the last reline and the hours it took.

  1. 1

    Load last stop's job list

    Import the last reline's job list from Excel, or the schedule as Microsoft Project XML; MaintWiz is interoperable with Primavera P6.

  2. 2

    Fix the restart time

    Set the date that cannot move and let the critical path, float and baselines show what drives it.

  3. 3

    Set the gates

    Configure the seven readiness gates to your rules: materials, resources, predecessors, tools and scaffold, permits and isolations, scope and engineering, and go.

  4. 4

    Bring the crews in

    Planners, supervisors, technicians and contractors get role menus and the native mobile app, with offline work on transaction screens.

  5. 5

    Close and keep it

    Close-out records handover, lessons and deferred items, so the next stop is planned against this one.

MaintWiz is shutdown management software built into an AI CMMS, so the stop shares work orders, spares, ePTW permits and maintenance history with the rest of the plant. For the sector background, read mining shutdown planning.

FAQ

Frequently asked questions

What does mining shutdown software do?

It plans and runs a processing plant shutdown around the mill reline: the critical path, readiness of liners, tools and permits, shared lifts by crew and day, and the handover of every job between shifts.

Can MaintWiz plan a SAG or ball mill reline?

Yes. The reline is the critical path of the shutdown project, with its kits, tools, permits and crews checked by readiness gates before the window opens.

How does MaintWiz fit other plant jobs around the reline?

The Gantt and float map show which jobs have float, so flotation, thickener and conveyor work is scheduled around the reline without touching its path.

How are heavy lifts shared between shifts?

Shared tool pools and the look-ahead by crew show who has the crane and when, so clashes are seen before the shift starts.

How do shift handovers work in MaintWiz?

Each work order carries a handover note and an as-left summary, and shift handover lists show what passes to the next crew.

How are liners, tools and crews checked before the stop?

Readiness gates for materials, tools, permits and resources, and kit readiness by package, show what is ready and what is missing.

What happens to the plan when a liner fails early?

Bring the next reline forward from the last plan, re-check the gates for kits and crews, and the float shows what else must move.

Can we import a reline plan from Microsoft Project or Excel?

Yes. MaintWiz imports Microsoft Project XML and Excel task lists and is interoperable with Primavera P6.

How is MaintWiz priced?

MaintWiz is a subscription that grows with your users, sites and modules, with a fixed implementation fee; ask for a written quote at a demo.

Can MaintWiz use the equipment records we already have?

Yes. Equipment lists and job lists load from Excel, schedules from Microsoft Project XML, and where the plant runs SAP, assets and their codes sync from SAP PM or MM.

Have the reline ready before the window opens

Book a demo and bring your last reline plan. We will show the kit gates, the lift plan and the handover on your own mill.