Skip to content
MaintWiz: Innovating Industrial AI

Execution

Shutdown Daily Meeting Agenda: Plan of the Day for Turnarounds

Short answer

A shutdown daily meeting, often called the plan of the day, is the one decision meeting of each turnaround day. Held after the morning handover and chaired by the shutdown manager, it takes seven items in a fixed order: safety and SIMOPS, progress, critical path, look-ahead, blockers, discovered work, and cost and actions. Every item ends in a decision or an action with an owner and a time.

How MaintWiz helps: MaintWiz shows the 72-hour look-ahead, readiness by gate, the critical path with float and the end-of-day summary from one plan, so the meeting reviews one set of numbers.

By · Technical review: Murali Nerur Pasupathy · Published · Last reviewed

What MaintWiz adds:72-hour look-ahead by crewReadiness by gateEnd-of-day summaryFindings to the planner

Rhythm

How does a turnaround day run around the daily meeting?

One decision meeting a day, fed by the shift handover and followed by crew briefings and the schedule update.

  1. 1Night-to-day handoverSupervisors hand over each job at the shift change.
  2. 2Plan of the dayThe decision meeting: safety, progress, critical path, blockers, scope.
  3. 3Crew briefingsToolbox talks and pre-job briefings at the work front.
  4. 4Afternoon schedule updatePlanners update progress at the status date and the look-ahead.
  5. 5Day-to-night handoverThe evening handover carries the day's decisions into the night shift.
A turnaround day: two handovers, one decision meeting, crew briefings and one schedule update, in a fixed order.

Morning plan of the day

Hold it after the night-to-day handover, so the meeting starts from the real state of the work, and early enough that decisions reach the crews before the first lift of the day.

Safety, permits and SIMOPS

Open with safety: incidents and near misses, permits that lapsed, isolations found wrong, and simultaneous operations that must not run together, such as hot work near a pressure test. On large stops the permit issuers hold their own short review before the main meeting.

Afternoon schedule update

Planners record progress as actuals against a status date with the logic intact, as GAO's schedule guide describes, so the next morning's meeting works from current float. 1

Evening handover

The day's decisions reach the night crews through the shutdown shift handover.

Agenda

Shutdown daily meeting agenda for turnarounds and outages

Seven items in the same order every day, each with an input, an owner and a decision, in about 35 minutes. The critical path gets the most time.

Shutdown daily meeting agenda with inputs, owners, decisions and minutes
ItemInput to bringOwnerDecisionMinutes
Safety and SIMOPSIncidents, near misses, permit issues, work that must not run together, hours against limitsSafety leadActions on hazards; clashes resolved; hours exceptions5
ProgressPercent complete against the baseline at the status datePlannerWhere the stop is behind, by area3
Critical pathJobs with zero or negative floatSchedulerRecovery actions and owners8
Look-aheadWork for the next 24 to 72 hours and its readinessArea leadsJobs released, jobs held with the reason6
BlockersPermits, parts, scaffold, cranes, crewsEach ownerOne owner and a due time per blocker6
Discovered workNew findings against the frozen scope, with time and costShutdown managerApprove, defer or reject5
Cost and actionsSpend and forecast; open actions from yesterdayCost controllerForecast at completion; actions closed2
If an item has no decision to take today, it gets one line and the meeting moves on.

Worked example

Worked example: day 9 of a 21-day turnaround

ILLUSTRATION: what the seven items produce on one morning.

ILLUSTRATION: worked daily meeting on day 9 of a 21-day turnaround
ItemWhat was reportedWhat was decided
Safety and SIMOPSOne near miss at the column top; hot work planned beside the exchanger hydrotest at 14:00Hot work moved to 16:00 after the test; scaffold toe boards checked by noon
Progress54 percent complete against 58 percent planned at yesterday's status dateArea B is behind; no change to the finish yet
Critical pathReactor catalyst unloading has minus one day of floatSecond vacuum truck brought in; night crew added to unloading
Look-aheadTwelve jobs for the next 72 hours; three fail the scaffold gateScaffold crew re-sequenced to clear the three by tomorrow
BlockersGaskets for two exchangers shortStores expedites with the supplier, answer by 15:00
Discovered workPitting found near an exchanger inlet nozzle, repair adds one day off the critical pathApproved through change control; inspector to sign the repair procedure
Cost and actionsForecast 2 percent over budget; five actions open from yesterday, four closedChange request raised for the nozzle repair

Inputs

What should be ready before the daily turnaround meeting?

The meeting is only as good as the numbers it starts from. Have one set of them, from the plan, before anyone sits down.

Updated schedule

Progress at the status date, float and the critical path, updated the afternoon before.

Readiness by job

Which jobs for the next 24 to 72 hours pass their gates: parts, permits, scaffold, crew.

Discovered-work log

Each new finding with its time and cost impact, ready to decide.

Open actions

Yesterday's actions with owner and due time, open ones first.

Progress, float and cost come from the shutdown daily report, which the meeting reads and acts on.

Which KPIs does the meeting review?

Keep it to the few that drive decisions: percent complete against plan, the schedule and cost indices, float on the critical path, open permits and SIMOPS clashes, the count of discovered-work items waiting, and incidents and near misses since the last meeting.

Attendees

Who attends the turnaround daily meeting, and who leads it?

The people who can take a decision or own an action, and no one else.

Who attends the turnaround daily meeting
RoleBringsTakes away
Shutdown or turnaround manager (chair)Priorities, decisions on discovered workDecisions recorded
Operations representativePlant state, handback dates, permits issuedWhat operations must release today
Planner and schedulerUpdated schedule, float, look-aheadChanges to make in the plan
Safety leadIncidents, near misses, permit and SIMOPS issuesSafety actions
Materials or stores leadShort parts and arrivalsExpediting actions
Contractor leadsTheir progress and blockersTheir actions and released jobs
Cost controllerSpend and forecastChange requests to raise

Contractor leads

Each major contractor sends one lead who can commit crews. Smaller contractors report through the area supervisor.

Power plant outages

On a generating unit outage, hold the meeting where the outage schedule is kept, often an outage control room, with the turbine and boiler OEM supervisors as leads for their packages.

Which meeting is which

Toolbox talk, pre-job briefing or daily meeting: which is which?

A turnaround runs several short meetings. Each has a different audience and a different output.

Turnaround meetings compared
MeetingWhoPurposeOutput
Toolbox talkA crew and its supervisorHazards and controls for the day's workCrew briefed and signed
Pre-job briefingThe crew on one jobThe steps, permit and isolations for that jobJob ready to start
Shift handoverOutgoing and incoming supervisorsState of every job, permit and lockSigned log
Daily meeting (plan of the day)Shutdown manager and leadsDecisions on safety, path, blockers, scopeActions with owners
Schedule updatePlannersProgress at the status dateUpdated plan and report
Weekly steering meetingSite managementBudget, forecast, major changesApprovals

Discipline

How do you keep the daily meeting short and useful?

The meeting fails in predictable ways. Each has a simple rule against it.

It runs long

Fixed start, fixed length; detailed problem solving goes to a follow-up with the people involved.

Numbers disagree

One source for progress, float and cost: the updated schedule at its status date.

Actions vanish

Every action has an owner and a due time, and open actions are read first the next day.

Scope creeps in

Discovered work is decided through change control, with its time and cost on the table.

Wrong people

Only those who can decide or act attend; everyone else gets the report.

It replaces handover

The meeting decides; the shift handover passes the state of each job.

In MaintWiz

How does MaintWiz run the daily meeting from one plan?

Everyone looks at the same plan, so the meeting spends its time on decisions.

  • The 72-hour look-ahead shows each crew's work and what is ready, in progress, blocked or critical.
  • Readiness shows by gate for every package: materials, resources, predecessors, tools and scaffold, permits and isolations, scope and engineering.
  • The command centre's end-of-day summary lists progress, the schedule index, forecast finish, blockers, open SIMOPS conflicts and emergent requests waiting.
  • Findings from the field reach the planner directly, ready for the discovered-work item.
MaintWiz: next three days by crew with the busiest zones
72-hour look-ahead by crew. Next three days by crew draws each task as a bar placed by planned dates, 8 Mar to 11 Mar, grouped under In-house crews, Apex Mechanical, Sterling NDT, Voltaic Electrical and ThermoServe. Colours mark ready not started, in progress, complete, blocked and critical.
MaintWiz: command centre with progress to date, end-of-day summary and reported blockers
Command centre: progress and blockers. Two panels. Progress to date plots earned man-hours against the baseline plan by day as a line. End-of-day summary lists progress, schedule index, forecast finish, work started and finished today, reported blockers, open SIMOPS conflicts and emergent requests waiting.

FAQ

Frequently asked questions

What is on a shutdown daily meeting agenda?

Seven items: safety and SIMOPS, progress against the baseline, the critical path, the look-ahead and its readiness, blockers, discovered work, and cost with open actions. Each ends in a decision or an action with an owner.

What is a plan of the day meeting?

The daily decision meeting of a shutdown, turnaround or outage, where the leads review the state of the work and agree what must happen in the next 24 hours.

Who attends the daily turnaround meeting?

The shutdown manager as chair, operations, planning and scheduling, safety, materials, the cost controller and one lead for each major contractor: the people who can decide or own an action.

How long should the daily shutdown meeting be?

Short and to a fixed time: the agenda above runs to about 35 minutes, with the most time on the critical path. Detailed problem solving moves to a follow-up with the people involved.

Should the daily meeting be in the morning or the evening?

Most stops hold it in the morning, after the night-to-day handover, so decisions reach the crews early. The schedule update runs in the afternoon so the next meeting has current float.

What is the difference between a toolbox talk and a pre-job briefing?

A toolbox talk covers the day's hazards and controls with a crew; a pre-job briefing covers the steps, permit and isolations for one job just before it starts.

Is the daily meeting the same as the shift handover?

No. The handover passes the state of each job, permit and lock between supervisors at every shift change; the daily meeting takes decisions once a day.

How is discovered work decided in the meeting?

Each finding comes with its time and cost impact, and the shutdown manager approves, defers or rejects it through change control, so the frozen scope and the baseline stay meaningful.

Which KPIs should the daily turnaround meeting review?

Percent complete against plan, schedule and cost indices, float on the critical path, open permits and SIMOPS clashes, discovered-work items waiting, and incidents and near misses since the last meeting.

Who keeps the action log?

The planner or the shutdown coordinator records each action with an owner and a due time and reads the open ones first at the next meeting.

Sources

Sources

GAO's schedule guide read on 7 November 2026. The worked day is for illustration.

  1. US Government Accountability Office, GAO Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G)

Run the daily meeting from one plan

Book a demo and bring last turnaround's schedule. We will show the look-ahead, the gates and the end-of-day summary your meeting would read.

Book a demo