Night Shifts and Fatigue in a Shutdown: Hours and Rest Limits

Short answer

Treat night work as a controlled risk with written limits. HSE guidance suggests capping shifts at 12 hours including overtime, limiting long night shifts to 2 or 3 in a row, and keeping demanding or safety-critical work out of low-alertness hours. API RP 755 sets outage ceilings of 14 hours a shift and 182 hours per work-set, with a documented exception process. Record actual hours daily.

How MaintWiz helps: The MaintWiz shutdown module carries this work as work packages with checklists, readings and photos, permits and readiness gates, so the result stays with the work order.

By · Technical review: Murali Nerur Pasupathy · Published · Last reviewed

What MaintWiz adds:Critical path and floatReadiness gatesPermits and isolationsChecklists with readings

Published limits

What hour and rest limits do the published sources set?

HSE gives guidance; API RP 755 is a recommended practice for refining and petrochemical process-safety roles, and neither is a fixed legal cap.

Published hour and rest controls
SourceControlPublished value
HSE HSG256 (2006)Maximum shift length12 hours including overtime; 8 hours for night or safety-critical, demanding work
HSE HSG256 (2006)Consecutive shifts5 to 7 days for standard shifts; 2 to 3 for long, night or early-start shifts
HSE HSG256 (2006)Day-to-night changeoverMinimum 2 nights' full sleep
UK Working Time Regulations (as stated in HSG256)Daily rest11 consecutive hours
API RP 755, 2nd edition (2019), normal operationsHours cap14 hours per shift and 92 per work-set (105 for straight days); 34 hours off, or 46 if the set had 4 or more nights
API RP 755, 2nd edition (2019), outagesHours cap14 hours per shift and 182 per work-set; 34 hours off after the work-set

Planning

How should the shutdown plan handle night shifts and fatigue?

HSE names plant shutdown as a pressure that pushes people to work extended hours, so the limits belong in the plan before the stop starts.

  • Write the hour limits into the shutdown plan and the contractor requirements: maximum shift length, consecutive shifts, minimum rest.
  • Avoid permanent night shifts and allow at least 2 nights of full sleep when crews switch between days and nights.
  • Keep demanding, dangerous or safety-critical work out of the low-alertness hours and the end of long shifts.
  • In refining and petrochemical process-safety roles, apply API RP 755: on-site contractors in those roles need equivalent fatigue risk controls.
  • Define an exception process for hours above the limit: a documented risk assessment, a mitigation plan, and approval by the supervisor and another manager.
  • Record actual hours worked each day, including overtime and contractor crews, and review them at the daily meeting.

FAQ

Frequently asked questions

Is there a legal maximum number of consecutive night shifts for a shutdown?

HSE's guidance is advice rather than a fixed legal cap: it suggests limiting long or night shifts to 2 or 3 in a row. The Working Time Regulations set 11 hours' daily rest. API RP 755 is a recommended practice, not law.

Do API RP 755 limits apply to contractors during a turnaround?

Yes for contractors in process-safety-sensitive roles: the API fact sheet says on-site contractors in those roles must have fatigue risk management equivalent to its criteria.

How long should crews rest after a block of shutdown shifts under API RP 755?

A work-set is complete after 34 hours off, or 46 hours off in normal operations if it included 4 or more night shifts. For outages the fact sheet lists 34 hours.

What should a shutdown plan do when hours must exceed the limit?

API RP 755 describes an exception process with a documented risk assessment and mitigation plan, with supervisor and management involvement.