Key takeaways
- Roles: steering committee, TPM lead or office, pillar owners, area teams, champions, and the sponsor who is the plant head.
- Small overlapping groups link the levels: a leader at one level is a member of the group at the level above.
- Define who is responsible, accountable, consulted and informed for each recurring activity, and keep it short.
- Time is the real test: owners need time in their working week and authority to act, or the roles are titles only.
- MaintWiz sets roles and entitlements per customer, so each owner sees their own views and overdue alerts, with a named owner on every tag, work order and audit.
Promotion organisation
What is a TPM promotion organisation?

TPM, the method JIPM promotes, is carried by an organisation built for it, usually called the promotion organisation. It sits across the line organisation and gives each pillar a leader, each area a team and each level of management a part in the programme. A common feature is overlapping small group activities: the leader of a group at one level is a member of the group at the level above, so that policy flows down and information flows up through people who attend both. The promotion organisation is the standard TPM structure: a steering committee, a TPM lead, a pillar owner for each pillar and area teams (Figure 1).
Downloads
TPM organisation templates: RACI matrix, pillar charter and champion routine
ExcelTPM promotion organisation and RACI matrixNine roles across 40 TPM activities with a one-accountable check
- Sheets
- Dashboard, Inputs, Pillars, RACI, Forums, Small groups, Org chart, Read me
- A4
- Version
- v1.0, 2 November 2026
PowerPointTPM kick-off presentation for the plant team (15 editable slides)Launch TPM with your plant team using 15 editable slides: why we start, the eight pillars, 16 major losses, who does what, first 90 days.
Inside: Why we are starting TPM and what TPM is · The eight pillars, OEE and the 16 major losses · Promotion organisation, who does what and the pilot area · Jishu Hozen 7 steps and 5S · First 90 days, what we will measure and what we ask of you this week
- Slides
- editable, 16:9
- A4
ExcelPlant Head monthly TPM review packRun the monthly TPM review on a correct PQCDSM scorecard, with pillar status, decisions and a one-page board extract
- Sheets
- Dashboard, Inputs, Pillar status, KPI scorecard, Decisions, Agenda, Board extract, Read me
- A4
- Version
- v1.1, 4 November 2026
ExcelTPM pillar charter and annual planStart each of the eight pillars from a charter with its aim, zero goal, step model and three lead KPIs
- Sheets
- Dashboard, Inputs, Charter, Charter AM, Charter FI, Charter PM, Charter QM, Charter ET, Charter SHE, Charter EEM, Charter OT, Pillar summary, Annual plan, Read me
- A4
- Version
- v1.0, 2 November 2026
ExcelTPM Champion weekly routine, Gemba log and action trackerA daily-to-quarterly routine for the TPM Champion, with step audits and Yokoten
- Sheets
- Dashboard, Inputs, Routine, Gemba log, Actions, Read me
- A4
- Version
- v1.0, 2 November 2026
Org chart
What does a TPM organisation chart look like?
A TPM organisation chart has three levels joined by overlapping small groups. The plant head chairs the steering committee; the TPM office and one committee per pillar sit in the middle; area Jishu Hozen circles, led by the line leader with a TPM champion, sit on the floor. Each leader is a member of the group one level up.
Roles
What are the roles in a TPM programme?
| Role | Duties | Typical time |
|---|---|---|
| Sponsor (plant head) | Announces the decision, sets policy and targets, chairs the steering committee, removes obstacles, visits the floor | Regular, visible, scheduled |
| Steering committee | Reviews progress, approves the master plan and resources, resolves cross-functional issues | Monthly or quarterly meeting |
| TPM lead or office | Runs the programme, keeps the master plan, definitions and measures, coordinates pillars, trains and coaches | Full or part time, depending on size |
| Pillar owner | Plans and reports on one pillar, runs its audits and projects, coaches area teams | Part of the working week, protected |
| Area or line leader | Leads the area team, releases time, owns the area's tags, standards and results | Daily |
| TPM champion | Coaches teams on the floor, keeps routines alive, collects questions and tags, helps the audits | Part of the week |
| Operators and technicians | Run the routines, raise tags, take part in projects, write one point lessons | In the shift |
| Finance partner | Agrees the values used for losses and checks savings on agreed definitions | As needed |
| HR and training | Supports the skills matrix and the training plan | As needed |
Titles vary: some plants call the TPM lead a TPM head or coordinator, and some give each pillar a pair of owners, one from operations and one from maintenance. What matters is that every pillar and every area has a named person (Figure 3).
RACI table
What does a RACI table for TPM activities look like?
RACI marks who is Responsible (does the work), Accountable (answers for the result, one person per activity), Consulted (gives input before) and Informed (told after). Adapt the RACI to your plant's pillars and areas.
| Activity | Sponsor | TPM lead | Pillar owner | Area leader | Operators | Maintenance |
|---|---|---|---|---|---|---|
| Set policy and targets | A | R | C | C | I | I |
| Keep the master plan | A | R | C | I | I | I |
| Define OEE and loss rules | I | A | R | C | C | C |
| Run daily routines and raise tags | I | I | C | A | R | C |
| Close red tags | I | I | C | A | I | R |
| Audit a step or pillar | I | C | A | R | C | C |
| Run a focused improvement project | I | C | A | C | C | R |
| Update standards after a change | I | I | C | A | R | R |
| Review monthly results | A | R | R | C | I | C |
Only one A per row. If two people are accountable, neither is. Review the table when the programme adds a pillar or an area.
How MaintWiz assigns the roles
MaintWiz, an AI CMMS built for TPM, puts a named owner on every tag, work order and audit, so the RACI above becomes a record. Roles and entitlements are set per customer: the steering group, pillar owners and operators each see their own views and overdue alerts, and every pillar has a clickable dashboard. Tag owners work in abnormality management. Book a demo to see the steering group's view on your own records.
What meeting cadence does TPM need?
The TPM meeting rhythm
From the daily area meeting to the steering committee
- Daily, at the equipmentArea meeting
Area leader, operators, champion. Inputs: Tags and the last shift's losses.
- WeeklyPillar meeting
Pillar owner and members. Inputs: Audits, projects and blocked items.
- Weekly or fortnightlyTPM office review
TPM lead and pillar owners. Inputs: Cross-pillar issues and training needs.
- Monthly or quarterlySteering committee
Sponsor, TPM lead, pillar owners, finance. Inputs: Results, decisions and resources.
- ScheduledGemba walk
Sponsor or senior leader with the area leader. Inputs: Tags and standards, asked of operators.
maintwiz.comAI CMMS built for TPM
WhatsApp us
+91 93459 29168
Book a demo
| Meeting | Who | How often | What it covers |
|---|---|---|---|
| Area meeting | Area leader, operators, champion | Daily, short, at the equipment | Tags, loss of the previous shift, today's routine, one problem |
| Pillar meeting | Pillar owner and members | Weekly | Plan against status, audits, projects, blocked items |
| TPM office review | TPM lead and pillar owners | Weekly or fortnightly | Cross-pillar issues, definitions, training needs |
| Steering committee | Sponsor, TPM lead, pillar owners, finance | Monthly or quarterly | Results, decisions, resources, audits passed |
| Gemba visit | Sponsor or senior leader, area leader | Scheduled | Walk the area; ask operators about the tags and standards |
Size
How big should the organisation be?
A small plant may have a part-time TPM lead, three or four pillar owners who each take two pillars, and champions in each pilot area. A multi-site business adds a group lead who sets the common definitions and runs cross-plant audits. Avoid adding roles faster than the programme can fill them with people who have time. Start with the pillars that the pilot area needs, such as autonomous maintenance, planned maintenance and focused improvement, and add owners as pillars start.
- One TPM lead with real authority beats a committee of busy people.
- Pair an operations owner with a maintenance owner on pillars where the two functions meet.
- Name a deputy for each role so that holidays do not stop the cadence.
- Include finance early so that loss values are agreed before they are quoted.
Common failures in TPM organisation
- Titles without time: owners are given the pillar on top of a full job.
- A sponsor who announces the programme and then disappears.
- A TPM office that does the work instead of coaching the line.
- No link between levels, so decisions do not reach the floor and problems do not reach the committee.
- Pillar owners all from maintenance, so operations do not own the routines.
- Too many meetings with the same attendees and no decisions.
- Measures that are not defined, so the steering committee debates the numbers instead of the actions.
Score your organisation in ten minutes with the free TPM self-assessment.
FAQ
Frequently asked questions
What are the roles in a TPM programme?
The main roles are the sponsor (plant head), the steering committee, the TPM lead or office, pillar owners, area or line leaders, TPM champions and the operators and technicians who run the routines. Finance and HR support.
What does a TPM champion do?
A TPM champion coaches teams on the floor, keeps the routines alive, collects questions and tags, helps with audits and links the area to the pillar owners. It is usually a part-time role carried by someone respected in the area.
What does a pillar owner do?
A pillar owner plans and reports on one pillar: sets its activities, runs its audits and projects, coaches area teams and presents status to the steering committee. The owner needs protected time and authority to act.
What is a TPM steering committee?
The steering committee is the leadership group chaired by the plant head. It approves the master plan and resources, reviews results and audits, and resolves cross-functional obstacles, usually meeting monthly or quarterly.
What is a RACI matrix in TPM?
A RACI matrix lists activities and marks who is responsible, accountable, consulted and informed. Only one person is accountable per activity. It prevents gaps and duplication between operations, maintenance and the TPM office.
How many people does a TPM office need?
A one-plant site starting three pillars usually runs a part-time TPM lead, three or four pillar owners who each take two pillars, and a champion in each pilot area. Meetings run daily at the area and weekly by pillar. Add roles only as fast as people with time can fill them.